Sydney Motorway Interchange

Case Study

Sector: Infrastructure (Roads)
Location: NSW
Client: Confidential
Project Value: Multi-billion (AUD)
Project Duration: 5+ years

  • A complex underground road interchange formed part of a larger city-shaping motorway. Multiple contractors worked under pressure to deliver within ambitious timeframes.

  • Scope creep, shifting design requirements, and interface issues across multiple parties caused disputes over time and cost entitlements. Documentation was fragmented and the client faced mounting payment delays.

  • Conducted a forensic review of records, contracts, and statutory entitlements.

    Structured claims using a cause–effect–quantum framework.

    Provided independent peer review to strengthen submissions.

  • Developed robust claim documentation and adjudication submissions aligned with both contract and statutory requirements.

  • Developed robust claim documentation and adjudication submissions aligned with both contract and statutory requirements

  • Disciplined record-keeping and structured claims are critical in multi-party infrastructure projects.

    Independent review of entitlements reduces risk of rejection.